本次照明施工主要分为装置区照明和道路照明两部分,装置区照明灯具类型、回路比较多施工时必须严格按照照明平面图和照明系统图进行施工,照明配管采用镀锌钢管全封闭形式。道路照明路灯基础部分由其他单位施工,目前全场地下工程尚未完全结束施工时必须注意其它专业的相互配合。The overall outdoor lifting is planned to be started from the middle of October and completed by the middle of December. The lightings are mainly for the plant area and the roads. The lamps in the plant area have more loops so that the construction must be strictly in accordance with the lighting plans and system drawings and the lighting piping shall use galvanized steel pipes with complete closure. The street lamp foundation shall be constructed by another unit. At present, because the overall underground project hasn’t been finished, the construction unit must pay attention to cooperate with other disciplines.