内容简介 国外2×220MW火电厂工程EPC总承包合同,中英文对照合同,WORD格式,共64页。 Time completion Plant for : 电厂竣工时间 - Unit No.1: 36 (thirty six) months from effective date of Contract. 1号机组:从合同生效之日起36个月; - Unit No.2 and the whole Plant: 42 (forty two) months from effective date of Contract. 2号机组及整个电厂:从合同生效之日起42个月; Contractor shall commence work on the XXCoal-fired Thermal Power Plant right after the Effective Date 承包商应该在合同生效之日起,开始执行XX燃煤火电厂总包合同。 The Contract shall enter into full force and become effective on the date when all of the following conditions have been fulfilled: 以下条件满足后,合同才能全面生效: 1) this Contract Agreement has been signed for and on behalf of YY and the Contractor; YY集团和承包商代表签署合同协议。 2) The Bidder has submitted to YY the Performance Security and Advance Payment Guarantee ; 投标商向YY集团支付履约保函和预付款保函。 3) The Bidder has received the Advance Payment from YY in accordance with relevant terms of the Contract. 投标商根据合同条款的规定,从YY集团收到预付款。