3) 由C581引出10路10kV线路,分别为A507的四台变压器,B551的两台变压器,B553TDA装置氢气压缩机2台,C521盐酸装置氯气压缩机1台,盐酸压缩机1台提供电源。其中,变压器回路采用10kV截面为185mm2的三芯铠装电缆,马达回路采用10kV截面为95mm2的三芯铠装电缆。以上电缆线路均沿规划路径埋地敷设。10 10kV lines led from C581 are used to supply power to A507's four transformers, B551 two transformers, B553TDA 2 sets of hydrogen compressor unit, C521 hydrochloric acid chlorine gas compressor unit, and hydrochloric acid compressor unit respectively. Among them, transformer circuit uses x 3-core armored cable with 10kV cross-section 185mm2, motor circuit uses three-core armored cable with 10kV cross-section 95mm2. All cable lines will be laid underground along the planning path.
Bidder shall, under the approval of municipal authority, implement the construction of No. 2 water supply project (drinking-water plant) with the capacity of 150,000 cubic meters daily water supply, and it is intended that part of the proceeds of the loan from World Bank will be applied to eligible payments for the purchase of equipment in accordance with the contract of project (Brief Description of the Goods herebellow ).
5) 控制电缆回路: Control cable circuit: 安装在HCL装置现场的3.6MW马达上的电流信号通过一根直埋敷设的铠装控制电缆直接接入10KV开关柜。The current signal installed on 3.6MW motor in the HCL devices site passes through a buried armored control cable direct access to 10KV switchgear. 由变压器出线柜去C581以外的变压器,采用两根分别为10*2.5mm2、4*2.5mm2屏蔽铠装控制电缆,由中压转接柜引出,与中压电缆同路径敷设至相关变压器室。其中,10*2.5mm2电缆直接接至温控箱,4*2.5mm2电缆可集中从某间变压器室引出,沿桥架至相关PCS楼ATS柜。Transformer outlet cabinets are connected to other transformers not in C581 by using two 10 * 2.5mm2, 4 * 2.5mm2 shield sheathed control cable respectively. The 10 * 2.5mm2 cable directly is connected to the temperature control box and 4 * 2.5mm2 cable are led out from transformer room, along the bridge to the relevant PCS floor ATS cabinet.
XX Phase 3 Expansion Project is located on Changzhou City Jiangsu province of P.R.C which includes Side By Side Plant, Office building, and Guard, road, underground utility ,bicycle shed etc. XX三期扩建项目位于中国江苏省常州市,其中包括组装车间,办公室,门卫,道路地下管线,停车棚等。 Conformance with the latest editions and / or amendments of PRC codes and standards will be considered as a minimum requirement: 在施工过程中将结合本项目的特点及相关规范开展现场工作,并以此为最低标准,同时将严格遵守中国法规及标准的最新版本或其增补版。