本工程共有碳钢管道7581m,碳钢管道焊接是本工程施工的重点,直接影响施工质量的好坏,所以我们应高度重视,保证工程的施工质量。 Carbon steel piping in this project is 7581 meter long, so welding work for carbon steel piping is one of the most important work in the construction. We will pay high attention on this, to guarantee quality of this project.
镀锌钢管明敷设 Open Lay of Galvanized Steel Pipe 本工程明敷设钢管均采用了镀锌钢管明敷设工艺。 All open-lay steel pipes in the project adopt the open-lay technology of galvanized steel pipe.